Construction Update – Stockton University Academic Quad Expansion Project
The Stockton Project is moving along with footings and foundations being complete for both buildings. The Unified Science Center II underground plumbing and electric is close to being complete, concrete slab on grade will follow. For the Classroom Building, backfilling is being completed and underground plumbing and electric work commenced.